Explore the bunker construction progress.

Dec 2024: Outer wall pour.

July 2024: Outer wall formwork commences. Due to the thickness of the walls, they will be constructed in three stages (outer, inner, then infill).

June 2024: Rebar to support the walls is installed.

May 2024: The floor is complete. The rectangular cutout is for the base-frame that will hold the linear accelerator in place.

April 2024: Before the bunker floor can be poured, rebar has to be placed.

March 2024: Ductwork is placed from the treatment room to the control area.

February 2024: Rebar is placed to form the control area floor.

January 2024: Formwork is constructed at the front of the bunkers. This will provide a platform for the control and equipment rooms with storage underneath.

November 2023: The foundations are complete, after removal of the formwork

June 2023: The foundation concrete pour nears completion

May 2023: Foundation formwork is constructed

April 2023: Foundation rebar nears completion

February 2023: Foundation rebar installation commences

January 2023: Excavations for the bunker foundations are completed

November 2022: We hold the official groundbreaking ceremony

January 2021: The site is cleared and levelled